Demolition of Three Two-Storey Timber Staff Housing Buildings

Hokurei Construction demolished three ageing, two-storey timber buildings that had been used as company staff housing. The work included an asbestos survey, tree and root removal, demolition and waste sorting, followed by levelling and handover of the cleared site.

The buildings and the client’s brief

The client was a company for which we had already carried out office building work, maintenance and renovations over many years. The housing buildings had deteriorated, and the request was to demolish them and hand over the cleared site.

The Japanese project record notes that the future use of the land had not been decided, and that no new-building proposal had been requested.

Staff housing buildings before demolition, with trees and a utility pole beside the road
Before demolition: the staff housing buildings viewed from the road.

Asbestos survey and tree removal before demolition

Before demolition, the exterior wall coating was tested for asbestos. The possibility of asbestos in the building interiors was also taken into account when allowing for the necessary protective measures and their cost.

Trees that had grown large on the site were a particular concern for the client. They were cut down before demolition began, and the roots were dug out and removed with machinery.

Demolishing three buildings beside neighbouring homes

The site was surrounded by apartments and detached houses, so particular attention was paid to noise and dust control. The three buildings were demolished in parallel. Road access allowed large trucks to park alongside the site, which helped the removal of demolition waste.

An excavator demolishing timber housing, with bags of demolition waste in front
During demolition: an excavator at work, with bags of demolition waste in front.

Sorting and removing demolition waste

Waste was separated by type for disposal, including timber, plasterboard, concrete rubble, exterior wall materials, mixed waste and plastics.

Handover of the cleared site

All three buildings were demolished, demolition waste was removed, and the ground was levelled before the cleared site was handed over.

The cleared and levelled site after demolition, with neighbouring buildings around it
After demolition: the cleared and levelled site.

Discussing a demolition project

Hokurei also accepts enquiries about demolition of company-owned staff housing, dormitories, offices and warehouses. The proposed approach depends on the size and location of the buildings, the asbestos survey, and whether trees or items left in the property need to be removed.

You can ask about demolition and levelling even if the future use of the site has not yet been decided.

For enquiries in written English, use our English inquiry form. Phone calls are in Japanese.

Explore our services or read about Hokurei Construction.

Read the original Japanese demolition case study.